Activity | 时长 | From | To |
---|---|---|---|
Knowledge transfer on the requirements to the team 将需求的知识传递给团队 |
2天 | 10-Oct-22 | 11-Oct-22 |
Project kick off 项目启动 |
1天 | 12-Oct-22 | |
Configuration + Unit Test 配置+单元测试 |
7天 | 12-Oct-22 | 18-Oct-22 |
E2E:Inbound Process 端到端:入库流程 |
20天 | 12-Oct-22 | 31-Oct-22 |
E2E : Packing & Quality Check 端到端:包装和质量检查 |
20天 | 1-Nov-22 | 20-Nov-22 |
E2E:Outbound Process 端到端:出库流程 |
12天 | 21-Nov-22 | 2-Dec-22 |
Build Results Review and QA deployment + Training 构建结果审查和QA部署+培训 |
2天 | 4-Dec-22 | 5-Dec-22 |
QA-Readiness 质量保证-准备 |
1天 | 6-Dec-22 | |
UAT + Integration test 用户验收测试 + 集成测试 |
15天 | 7-Dec-22 | 21-Dec-22 |
Production Deployment 生产部署 |
1天 | 5-Jan-23 | |
Cut over 切换 |
3天 | 6-Jan-23 | 8-Jan-23 |
Go Live 上线 |
1天 | 9-Jan-23 |